Only One in Two IIP Proceedings Ends Successfully

25 November 2026

An analysis of over 600 proceedings concerning Integrated Investment Plans (IIP), conducted by Walter Herz, shows that the procedure remains a challenging and time-consuming tool for delivering real estate developments. The success of a project depends not only on its parameters but also on its alignment with the municipality’s spatial planning policy, infrastructure conditions and the scope of the investor’s obligations.

The Walter Herz analysis covered over 600 proceedings across 230 municipalities in all 16 Polish provinces. It covered cases concluded by mid-November this year, for which sufficient documentation was available to evaluate the outcome of each proceeding, its duration and the obligations set out in the corresponding urban planning agreements.

The study found that only half of the cases reviewed resulted in the adoption of an investment plan, while the average processing time was nine months. The outcome depends not only on the project’s parameters but, above all, on its alignment with the municipality’s spatial planning policy, infrastructure availability, the local authorities’ position and the scope of commitments the investor is prepared to undertake.

Residential developments accounted for the largest share of applications, with 330 cases recorded. Commercial and retail projects followed closely, totalling 317. The register also included 89 tourism and leisure developments, 72 photovoltaic projects, 55 warehousing and manufacturing schemes, 31 renewable energy projects, 19 agricultural developments, 17 public and educational facilities, 12 infrastructure projects, seven wind power plants, six extraction projects and three senior care facilities. As individual proceedings may cover more than one type of development, the combined total across categories exceeds the number of cases analysed.

Approximately 50 per cent of concluded proceedings resulted in plan adoption

Half of all cases analysed remain ongoing. Of the 300 applications that have been processed, 122 resulted in the adoption of an investment plan by the municipal council, another 122 were closed without a plan being approved, and 12 cases involved the annulment of applications or resolutions already adopted.

The figures highlight the significant procedural risks associated with the Integrated Investment Plan (IIP) mechanism. Under the applicable regulations, investors must submit a draft IIP together with their application, having financed its preparation in advance.

– A significant risk for investors lies in the discretionary nature of the municipal council’s initial decision. The council may refuse to approve the commencement of IIP preparation without providing justification, and no appeal is available against such a refusal. Administrative courts dismiss complaints challenging these decisions. Moreover, the council may withdraw its approval at any point before the urban planning agreement is signed, effectively bringing the proceedings to an end. An additional risk stems from the governor’s supervisory powers, under which a resolution may be declared invalid within 30 days. This makes preliminary consultations with local authorities particularly important. Although not a formal statutory stage, discussions with the municipality before submitting an application and paying for the plan can help establish its actual position and assess whether the project has a realistic prospect of securing political and planning approval – says Katarzyna Tencza, Transaction Director at Walter Herz.

The average waiting time for a decision exceeds nine months

In geographical terms, the largest number of applications concerned the Malopolskie province, with 121 cases, followed by Warminsko-Mazurskie, with 91, and Mazowieckie, with 82. A further 55 cases were recorded in Pomorskie, 48 in Dolnoslaskie, 40 in Wielkopolskie, 30 each in Slaskie and Zachodniopomorskie, 23 in Kujawsko-Pomorskie, 19 in Lubelskie, 18 in Podlaskie, 15 in Podkarpackie, 14 in Opolskie, 9 in Lodzkie, 7 in Lubuskie and 4 in Swietokrzyskie.

An analysis of 62 cases for which the documentation included both the application submission date and the date of plan adoption shows that half of the proceedings took between 6.6 and 12 months, equivalent to 199–360 days. The average waiting time for a decision was 273 days. The shortest proceeding was completed in just 63 days, while the longest lasted as many as 769 days.

Bartłomiej Zagrodnik, Managing Partner and CEO at Walter Herz, points out that, from an investment perspective, it is essential to distinguish between the development potential indicated in an application and the development opportunities formally secured through an adopted plan. This distinction is particularly important given that the boundaries of the development area, building parameters and scope of infrastructure commitments may change at different stages of the proceedings.

– The analysis shows that the Integrated Investment Plan (IIP) offers investors an opportunity to deliver large-scale projects across various real estate sectors, but requires thorough preparation. With the average approval process taking more than nine months, investors incurring design costs before the municipal council makes its decision, and no guarantee that the plan will ultimately be adopted, early assessment of the property’s development potential, its compliance with the general municipal plan, infrastructure availability and the local authorities’ position is essential. Only by considering all these factors together can investors realistically assess a project’s value and the risks associated with moving forward with its development – says Bartłomiej Zagrodnik.

Residential and commercial developments dominate

The highest level of investor activity was recorded in the residential sector, which accounted for 330 applications. For these projects, alignment with the provisions of the municipality’s general plan is a key consideration. Where a general plan has already been adopted, residential development areas under an Integrated Investment Plan can only be designated in locations where each plot meets specific accessibility standards. These include access to a primary school and public green spaces. Municipalities may extend these requirements to include additional facilities, such as nurseries, kindergartens, primary healthcare centres and public transport stops. The required facilities may either already exist or be planned for delivery under a local spatial development plan.

The main reasons for refusing approval of residential projects included restrictions arising from the municipality’s housing land capacity calculations, the scale of the proposed development, heritage conservation requirements and conflicts with existing local spatial development plans. Municipal councils also rejected applications that fell within the development parameters set out in the former spatial development studies, as well as projects in which investors proposed contributions valued at levels close to the estimated planning gain levy.

In the case of adopted residential Integrated Investment Plans, urban planning agreements most commonly required investors to finance or deliver public roads, pavements, car parks and bus stops. Less frequently, the commitments covered green spaces, sports facilities, water supply and sewage infrastructure, public buildings or school extensions.

The second-largest category comprised commercial and retail developments, accounting for 317 proceedings. A particular challenge for this segment is defining the role of the complementary development. Retail and service facilities can qualify as complementary developments only if they serve the needs of the primary investment. According to Walter Herz, retail parks rarely meet this requirement, limiting the scope for using the IIP mechanism for this type of investment.

Before initiating the procedure, investors should verify whether the municipality’s general plan designates the relevant area for service activities or large-scale retail. The latter category applies to facilities with a sales area exceeding 2,000 sq m. Correctly defining the boundaries of the Integrated Investment Plan is equally important. These may encompass not only the sites designated for the primary and complementary developments, but also properties owned by third parties, as well as roads and junctions used by customers and suppliers.

Road access is a key factor in the feasibility of warehouse and manufacturing projects

The analysed dataset included 55 proceedings concerning warehousing, logistics and manufacturing developments. In this segment, project feasibility often hinges on whether adequate access and traffic infrastructure can be provided to accommodate heavy goods vehicles.

The assessment should begin by establishing the classification of the public road and determining whether a suitable access point can be constructed. Equally important is obtaining an early indication of the road authority’s position on the proposed access arrangements to the property. The development concept should also account for alternative entrance options and designated parking and waiting areas for heavy goods vehicles.

For industrial and warehouse developments, including associated infrastructure, the minimum building footprint threshold is 1 hectare. Investors must also confirm that the municipality’s general plan permits the relevant type of development within the designated planning zone.

In practice, the success of an IIP application for a warehouse or manufacturing facility depends primarily on two factors: whether the proposed activity is permitted within the zone designated in the general plan and whether adequate transport access can be provided. Verifying these conditions before initiating the formal procedure helps investors avoid committing capital to projects that may ultimately prove impossible to deliver.

Renewable energy projects – a simplified procedure does not eliminate risks

The IIP proceedings register also included 72 cases involving photovoltaic farms and renewable energy installations. For renewable energy sources other than wind farms, the legislator has introduced a separate, simplified IIP procedure. It does not require a municipal council resolution approving the commencement of plan preparation, and the statutory period for public consultations is shortened to 14 days.

The rules are different for wind farms, for which an IIP always requires approval from the municipal council. Before submitting an application, investors should establish the land classification recorded in the Land and Building Register and verify whether the site is subject to land drainage, using the register of water management and drainage infrastructure. It is equally important to assess the positions of both the mayor and the municipal council regarding the proposed development at an early stage. In this segment, local authority support remains one of the key factors in mitigating investment risk.

Tourism and senior housing – crucial classification of the intended use under the general plan

The analysed proceedings also included 89 tourism and leisure developments and three projects related to senior care. For hotels, serviced apartments and senior living facilities, the classification of the intended use under the municipality’s general plan is particularly important. From a spatial planning perspective, a hotel is not classified as residential development, while its designation as a standard service facility depends on the provisions adopted by the municipality.

This distinction has direct implications for the investment’s business model. If an Integrated Investment Plan does not permit residential use within an area designated for tourism services, it may not be possible to obtain a certificate confirming the existence of an independent residential unit in an aparthotel. This issue should therefore be resolved when preparing the draft plan, before it is put to a municipal council vote. Any subsequent conflict between the assumptions underpinning the commercialisation strategy and the adopted planning provisions could significantly affect the property’s value and permitted use.

Investors planning to develop senior living facilities should, in turn, carefully verify the noise protection requirements applicable to the site designated for the building.

Land classification is important for biogas plants and agricultural developments

A further 19 proceedings concerned agricultural production and biogas plants. The possibility of locating a biogas facility depends on the provisions of the municipality’s general plan. Such developments are always permitted in economic activity zones, while agricultural production zones and certain other designated areas allow them only if the municipality has included the relevant land use in the supplementary profile.

Additional restrictions may arise from regulations governing the protection of agricultural land. As a general rule, converting land classified as agricultural classes I–III to non-agricultural use requires approval from the minister responsible for rural development. Investors should therefore establish the classification of all plots designated for installations, buildings and access roads before initiating the planning procedure.

The Walter Herz analysis shows that delivering a project under the Integrated Investment Plan framework is a demanding process involving both planning considerations and negotiations with local authorities. The profitability of an investment depends on a combination of urban planning parameters and the terms of cooperation with the municipality. For investors, the most important decision often comes before the application is even submitted. Committing capital to a procedure with no guarantee of approval should be preceded by a thorough assessment of the property’s development potential, legal and infrastructure conditions, and the municipality’s willingness to cooperate.